The “Accessory Building” that is being built behind the Discipleship Building has had the foundation poured. This week the grading was completed, forms placed, and concrete poured. It will now take seven days to cure. In three to five weeks the building itself will arrive and be assembled. After that power will be trenched from the Discipleship Building back to the Accessory Building. We hope to see that work completed by the end of June. The building can be occupied we will be moving the materials and tools from the current barn behind the Roseman House. Once everything is moved in the existing barn will be demolished and the required drive can be completed.
Accessory Building Update (4/17/2025)